Source Berlin Pankow Seitengreifer3 2

Machinery - MÜLLER Vibration Technology

EXTREMELY CRAMPED CONDITIONS WHEN PULLING BERLIN SHORING IN BERLIN-PANKOW

EXTREMELY CRAMPED CONDITIONS WHEN MOVING BERLINER VERBAU IN BERLIN-PANKOW

New residential buildings were built in Berlin on Prenzlauer Promenade. The excavation pit there was secured with Berliner Verbau, which had to be removed again by the customer after completion of the residential buildings in the fall of 2020. In particular, the removal of the H-beams and the associated removal were extremely tricky. There was only one narrow access road where the large excavator could not turn around. Accordingly, it could not turn around with the towed girders and load them onto the waiting truck. In addition, there was the danger posed by HEB 400 girders over 10 meters long if they ever started to swing. Therefore, the initial plan was to burn through the girders and shorten them accordingly. Thanks to MÜLLER Equipment, however, a much more sustainable and economical solution was found.

This demanding task could be solved with the MÜLLER MS-6 HFB SG without cutting through the beams. The compact and lightweight MÜLLER excavator-mounted vibratory pile drivers can be attached to all common excavators. Power is supplied via the on-board hydraulics and control is via the excavator's operating levers. The side grab is particularly advantageous in confined spaces. It does not have to be placed on profiles from above, but grips them from the side and fixes them at the same time. This eliminates the possibility of the pile driving or drawing material swaying.

On the construction site at Prenzlauer Promenade, the side grab was able to grip the H-beams laterally, pull them out of the ground and then place them between the chains of the excavator. The excavator pushed the girders through to the rear, where they were picked up by another excavator and loaded onto a truck.

Extremely cramped conditions make it difficult to pull HEB girders
Thanks to the side gripper, the carriers are fixed and do not oscillate
The beam is pushed under the excavator at the side grab and can be picked up and transported away from the rear.

you might also be interested in

  • Stokes Hill Wharf Fender Piles

    terra infrastructure supplied both our müller MS32HFV vibro and BSP CX110 impact hammer to Advance Civil and Engineering to install 22 x 32m long fender piles on their Stokes Hill Wharf upgrade.


    To the post
  • Linear shoring ensures large and safe working space

    Zur Sicherung der Baugrube und zur Erstellung des Sammlers verwendet das Unternehmen den gestuften Linearverbau von E+S.


    To the post
  • Back anchoring steel sheet pile wall with micropiles

    On the north bank, an armored steel sheet pile wall was to be placed in front of the existing seawall over a length of around 400 meters and tied back at specified points.


    To the post