NEUBAU SAMMLER - LINEAR SHORING ENSURES LARGE AND SAFE WORKING SPACE

In the provincial capital of Badajoz, located in the west of Spain, COPISA Constructora Pirenaica is realizing a good 800 meters long collector and several rainwater retention basins. The work, commissioned by the Ministry of Agriculture, Food and Environment, has a volume of almost 13 million euros and the projected construction time is nine months. To secure the excavation pit and construct the collector, the company is using the stepped linear shoring system from E+S, a terra infrastructure product brand.

A decision that pays off not only in terms of safety: In particular, the use of the so-called U-type roller units and the possibility of moving them in height according to the manufacturer's specifications ensures the necessary working space when laying the pipes with large nominal diameters.

Primarily due to forecasts on the development of the number of inhabitants in the large city of Badajoz, the performance of the central wastewater system was to be increased in the long term. There was also a need for action with a view to future heavy rainfall events. Two rainwater retention basins with a capacity of 20,000 cubic meters are to ensure that the necessary capacities will be available in the future. In addition, a new DN 2000 collector will be laid over a length of 815 meters. The 5 to 6 meter deep excavation pit with a clear width of 2.75 meters is secured by stepped linear shoring.

To secure the excavation pit, which was up to 6 meters deep, 18 modules of the linear shoring system, each 4 meters long, were used.

Large working space

In Badajoz, a total of 18 modules of the shoring system, each 4 meters long, are used. The use of the U-type roller unit ensures maximum clearance height and thus the greatest possible flexibility on the construction site. The component has excellent static properties and is extremely resilient. Depending on requirements, the roller unit can be moved steplessly in different construction phases in accordance with the static specifications.

Due to its U-shaped design - enormous cantilever lengths are possible - the roller unit makes very large pipe clearance heights possible. This results in many technical and economic advantages for the equipment and vehicles used on the construction site during the installation and removal of the shoring and when working in the excavation pit.

In any case, the construction partners are unanimous in their verdict on the shoring system used: Both the system itself and the good technical advice provided on site helped to reduce costs on the construction site.

Data & Facts

Client
In any case, the construction partners are unanimous in their assessment of the shoring system used: both the system itself and the good technical advice provided on site helped to reduce costs on the construction site.
Delivery
18 modules of stepped linear shoring (module lengths 4.00 m), linear shoring soldiers and U-type roller units

you might also be interested in

  • Just-in-Time Delivery for a Bridge Abutment

    A new bridge for overpassing the A3 freeway was built at the Offenbach junction. There were a total of three excavation pits for this new construction.


    To the post
  • Protecting valuable history with terra stop log system

    In a major project here in the hinterland of the Elbe, a combination of a new earth embankment and strengthening of the protective measures by means of demountable stop log elements has been realised.


    To the post
  • Rehabilitation of a Landfill

    For groundwater capture, the landfill was provided with sheet pile walls, which were coated on both sides and provided with a permanent interlock seal.


    To the post