DRESDEN-GHOLIS FLOOD PROTECTION SYSTEM.
In the years 2002 and 2013, the Gohlis district of Dresden was completely flooded by the river Elbe. To permanently protect this part of town, we installed a complete flood protection system which at the same time provides access to the meadows along the Elbe.
On sheet piling with a foundation of drilled piles, a massive concrete and stone wall was erected, fitted partly with demountable 200 x 100 tk stop logs. These have to withstand very high impact loads – up to 50 kilonewtons per 50 x 50 centimeters. In accordance with DIN 19712, double closures were provided for crossings and passages. The protective wall is around 880 meters long, with barrier heights of 2 meters and 0.60 meters.
To store the demountable flood protection system, we designed special pallets that can be loaded and unloaded using a forklift truck, wheeled loader, or mobile crane.
you might also be interested in
-
Rain Overflow Basin in Chemnitz
Renovation of sewer, electricity, gas, drinking water, lighting and communication and construction of a storm water overflow structure in the area of the traffic junction.
To the post -
Flood Protection for the Yuyao Community in China
In the municipality of Yuyao, the Yuyao River was equipped with mobile flood protection along a length of about 4,700 metres to improve the quality of life of the citizens.
To the post -
Demountable flood protection with the terra stop log system
A reinforced concrete plinth and a demountable flood protection wall will prevent flood-waters from threatening the building in future.
To the post