DIKE RETROFITTING IN MICHEALAU
In the municipality of Michelau, the existing flood protection was to be upgraded to the state of the art. The aim was to provide protection against floods that statistically occur once every 100 years.
We supplied the material for the second construction phase of the protection measure: This involved 675 tons of sealed steel sheet pile profiles tk L 603 DB, most of them four meters long. The approximately 1,250 planks had to be processed exactly on the specified date. As it is very difficult to deliver such large quantities on the exact day, around one third of the total quantity was made available as used material. In this way, delays in rolling could be compensated by a combination of used and new screeds.
In total, a flood line of about 1,500 meters was created. The above-ground part was clad by the executing contractor with a lattice wall containing a filling of limestones.
you might also be interested in
-
Raising the banks of the Moritzbach in Zwickau
In October 2015, the official handover of the flood protection system on the Moritzbach in the Pölbitz district of Zwickau took place. Protective walls were strengthened and raised on around 530 metres of the watercourse.
To the post -
Rain Overflow Basin in Chemnitz
Renovation of sewer, electricity, gas, drinking water, lighting and communication and construction of a storm water overflow structure in the area of the traffic junction.
To the post -
Just-in-Time Delivery for a Bridge Abutment
A new bridge for overpassing the A3 freeway was built at the Offenbach junction. There were a total of three excavation pits for this new construction.