Bild18

Temporary Flood Protection - terra stop log system

PROTECTING VALUABLE HISTORY WITH TERRA STOP LOG SYSTEM

PROTECTING VALUABLE HISTORY WITH TERRA STOP LOG SYSTEM.

Oppitzsch, a district in Strehla, a town with a 1000-year history and buildings dating from the Middle Ages, lies on a bend in the Elbe. In the past, this district was very important because this was where the main eastwest road crossed the River Elbe. But the town and its surroundings have always been battling against the changing forces of the river’s floodwaters.

In a major project here in the hinterland of the Elbe, a combination of a new earth embankment and strengthening of the protective measures by means of demountable stop log elements has been realised. Twelve aluminium stop log elements were produced for a double dyke opening with a clear opening of 3.60 meters and a water retention level of 1.24 meters. They are supported by posts cast into reinforced concrete piers. In the event of flooding, the flood defences with a protective height of 0.80 meters are closed off with 14 separate stop log closures up to the intended flood protection height over a total length of 55 meters.

Four aluminium stop log elements, which are supported in the reinforced concrete piers, are provided for each closure. The distance between the concrete piers is approx. 3.65 meters. All the demountable parts, accessories, erection aids and tools are stored in specially designed pallets in a roll-off container.

Data & Facts

Client
Saxony Federal State Reservoir Administration, Rötha Office
Planning
Ingenieurgemeinschaft WTU Bad Liebenwerda
Scope of supply
terra aluminium stop log system, 12 pcs; aluminium stop log closures, 14 pcs.
Fabrication
RSW Rosslauer shipyards, Rosslau
Contractor
Steinle Bau GmbH Oschatz, Löbau Branch

you might also be interested in

  • Safety in a double pack in Berlin-Frohnau

    It was an excavation support of record-breaking dimensions - all construction partners involved in the sewer rehabilitation project in Berlin-Frohnau agreed on this.


    To the post
  • Linear shoring ensures large and safe working space

    Zur Sicherung der Baugrube und zur Erstellung des Sammlers verwendet das Unternehmen den gestuften Linearverbau von E+S.


    To the post
  • Raising the banks of the Moritzbach in Zwickau

    In October 2015, the official handover of the flood protection system on the Moritzbach in the Pölbitz district of Zwickau took place. Protective walls were strengthened and raised on around 530 metres of the watercourse.


    To the post