Arctic 1

Machine Technology - MÜLLER Vibration Technology

BROUGHT IN ICE-COLD.

BROUGHT IN ICE-COLD.

Machine technology from terra infrastructure in use for the port in Western Siberia

The rising global demand for energy is raising hopes for liquefied natural gas (LNG), which has been significantly reduced in volume, as a future-oriented energy source. As part of the Arctic LNG 2 project, an LNG production facility is to be built on the Gydan Peninsula in northern Western Siberia. The Arctic LNG 2 plant intends to use the resources of the Salmanovskoye field, a structure containing 1.98 trillion m³ of natural gas and 105 million tonnes of liquid hydrocarbons. For this purpose, three technological lines for the production of liquefied natural gas with a total capacity of 19.8 million tonnes of LNG per year are being built at the Utrenny terminal. For the terminal work under extreme climatic conditions, terra infrastructure GmbH supplied powerful vibration technology.

High-performance vibratory pile drivers

Two MS-210 HHF and two MS-240 HHF vibratory units were used for driving steel pipes into the permafrost soil - they had diameters of 1.42 and 2.52 metres respectively with a pipe wall thickness of between 14 and 28 millimetres. Both are among the most powerful vibratory pile drivers currently available on the market. Units in the HHF series are ideal for use in changing geological conditions and are adjustable in steps. By increasing the static moment with interchangeable additional weights, different vibration amplitudes and frequencies can be adjusted to the soil profiles with the same centrifugal force. In order to supply the müller vibration units with energy, drive units are required in which diesel engines drive hydraulic pumps inside a sound-insulated housing. In Utrenny, four MS-1150 V power units were used, each equipped with the optionally available winter package.

In view of the arctic temperatures, this was particularly important because the preheating devices for the hydraulic oil and the cooling water of the diesel engine contained in the package protect the system components and thus increase their operational readiness and service life. The volume flow was passed on to the vibratory pile drivers via hose lines, each 120 metres long. In this way, it was possible to drive steel pipes into the ground at depths of between 25 and 60 metres. Here, four MS-U 180 GP clamping devices - mounted on an MS-KX 320 console - ensured a vibration-free connection of the pipes to the vibratory unit.

The construction process in Utrenny is taking place in a total of seven stages. From 2023 onwards, the LNG plant is to be commissioned step by step.

Leistungsstarke Technik auf einen Blick: Rechts im Bild ist das mit einem Winterpaket ausgestatteten MÜLLER-Aggregat MS-1150 V zu sehen. Über den Hydraulikschlauch wird die Vibrationseinheit MÜLLER MS-240 HHF angetrieben. Mit diesem Equipment lassen sich die Stahlrohre vergleichsweise einfach bis 60 Meter tief in den Permafrostboden einbringen.
Powerful technology at a glance: The MÜLLER MS-1150 V power unit equipped with a winter package can be seen on the right in the picture. The MÜLLER MS-240 HHF vibration unit is driven via the hydraulic hose. With this equipment, the steel pipes can be inserted comparatively easily up to 60 metres deep into the permafrost.


Extreme climatic conditions with temperatures down to minus 40 degrees Celcius prevail on the Gydan peninsula. The picture shows: the steel pipes as piling material, a MÜLLER vibration unit of the HHF series and an MS-1150 V power unit with hydraulic hose.


The MÜLLER MS-240HHF vibratory pile driver from terra infrastructure is one of the most powerful in the industry. Here it is waiting to be used for driving the large steel pipes into the permafrost.


Despite the 120 metre long hydraulic hoses, the volume flow from the drive units could be reliably transferred to the vibrators.


Vibration technology from terra infrastructure is helping to drive steel pipes into the permanent frost soil at depths of up to 60 metres on the Gydan peninsula.

you might also be interested in

  • Foundation for first nuclear power plant in Bangladesh

    In Ruppur, about 180 kilometres west of the capital Dhaka, the first national nuclear power plant is to secure Bangladesh's energy supply from the end of 2023.


    To the post
  • Saxony-Anhalt is also battening down its hatches

    Since the “flood of the century” in 2002, Saxony-Anhalt has completed a whole range of flood defence measures, especially for upgrading dykes. One weak spot was the Elbtor alongside the River Elbe in Schönebeck.


    To the post
  • Flood Protection System in Dresdens Old Town

    The city of Dresden lies on several rivers that have overflowed their banks at regular intervals in recent years. The city and state have therefore been investing in flood protection for years.


    To the post