SAFETY IN A DOUBLE PACK IN BERLIN FROHNHAU

SAFETY IN A DOUBLE PACK IN BERLIN-FROHNAU. DEEPER LINEAR SHORING SECURES CONSTRUCTION PIT 10 METERS DEEP

It was a construction pit safety measure of record-breaking dimensions - all construction partners involved in the sewer rehabilitation project in Berlin-Frohnau agreed on this. Carl Zauber Tiefbau GmbH had initially been commissioned by the Reinickendorf Civil Engineering Office to secure a so-called backfill site in the Waldsiedlung, which is characterized by individual buildings and villas. The subsequent camera inspection of the wastewater sewer and the resulting damage findings led to a follow-up order from Berliner Wasserbetriebe for the rehabilitation of the affected sewer section.

After examining various alternatives, the contractor used the e+s linear shoring system from thyssenkrupp Infrastructure to secure the construction work on the pipeline, which was up to 10 meters deep. Particularly worthy of mention here is the fact that two linear shoring units were coupled together to secure the excavation pit, complementing each other in their mode of action after installation. And this was done while ensuring the load transfer required for the enormous depths achievable with this method.

The damage was preceded by a rain event of the century, which had caused a two-day state of emergency in large parts of Berlin at the end of June 2017 with flooded cellars, flooded streets and waterfalls in subway stations. Causes like these ultimately also caused the paved road surface to sag

Viable concept developed

It was during this phase that the company became aware of linear shoring and found a competent partner in thyssenkrupp Infrastrucure, with whom it developed a viable concept for securing an excavation at this depth. The construction partners made use of this concept to secure the excavation pit in Berlin-Frohnau, using what is known as deeper linear shoring.

Deeper linear shoring, in which two shoring units are coupled together, combines the advantages of the linear shoring system into a high-performance functional principle, which was the obvious choice in view of the general conditions prevailing in the sewer construction project. Unlike conventional linear shoring, the first module, which is placed in the ground, consists of doubled pairs of beams connected to each other at the upper end by a tension adapter.

In the excavation pit thus secured, the damaged pipes could be replaced and, in addition, a shaft structure renewed before the excavation pit was successively backfilled while simultaneously pulling out the shoring elements.


you might also be interested in

  • Dike Retrofitting in Michelau

    In total, a flood line of about 1,500 meters was created. The above-ground part was clad by the executing contractor with a lattice wall containing a filling of limestones.


    To the post
  • Clear view: glass panels in Neufelderkoog

    Here, a flood protection barrier including glass elements protects the inhabitants and visitors from storm tides. The glass breaks up the appearance of the approximately 800 meters long flood defence wall.


    To the post
  • Raising the banks of the Moritzbach in Zwickau

    In October 2015, the official handover of the flood protection system on the Moritzbach in the Pölbitz district of Zwickau took place. Protective walls were strengthened and raised on around 530 metres of the watercourse.


    To the post