Gr Header Image 20190308 LB profile ankertechnik H rth 1

Steel Section - Sheet Piling

NEW CONSTRUCTION OF A SHEET PILE WALL FOR SLOPE STABILIZATION

NEW CONSTRUCTION OF A SHEET PILE WALL FOR SLOPE STABILIZATION

The gravity wall in Gennerstraße in Hürth was to be replaced by a sheet pile wall clad with L-stones in spring 2018. For the executing construction company, we took over the entire technical planning of the sheet pile wall and supplied the necessary material. A total of 54 tons of L604 steel sheet pile sections in lengths of six to 9.5 meters were used.

The construction work was carried out in sections, i.e. part of the existing concrete wall was demolished and the sheet pile wall was installed in its place. Due to the existing historical buildings, we used pre-drilling and vibration for the installation. We produced the required radius at a road intersection with seven construction piles from our own production.

The project was calculated to take four weeks to complete. Thanks to our customized logistics concept and high-performance machine technology, it was completed in only 18 days.

you might also be interested in

  • Foundation for first nuclear power plant in Bangladesh

    In Ruppur, about 180 kilometres west of the capital Dhaka, the first national nuclear power plant is to secure Bangladesh's energy supply from the end of 2023.


    To the post
  • Glass Wall in the Turmschanzenstrasse Area, Magdeburg

    To maintain the view of the river in the Turmschanzenstrasse area, we installed glass walls at various points consisting of individual glass panels in different sizes.


    To the post
  • Back anchoring steel sheet pile wall with micropiles

    On the north bank, an armored steel sheet pile wall was to be placed in front of the existing seawall over a length of around 400 meters and tied back at specified points.


    To the post