Gr Header Image 20190308 LB profile ankertechnik H rth 1

Steel Section - Sheet Piling

NEW CONSTRUCTION OF A SHEET PILE WALL FOR SLOPE STABILIZATION

NEW CONSTRUCTION OF A SHEET PILE WALL FOR SLOPE STABILIZATION

The gravity wall in Gennerstraße in Hürth was to be replaced by a sheet pile wall clad with L-stones in spring 2018. For the executing construction company, we took over the entire technical planning of the sheet pile wall and supplied the necessary material. A total of 54 tons of L604 steel sheet pile sections in lengths of six to 9.5 meters were used.

The construction work was carried out in sections, i.e. part of the existing concrete wall was demolished and the sheet pile wall was installed in its place. Due to the existing historical buildings, we used pre-drilling and vibration for the installation. We produced the required radius at a road intersection with seven construction piles from our own production.

The project was calculated to take four weeks to complete. Thanks to our customized logistics concept and high-performance machine technology, it was completed in only 18 days.

you might also be interested in

  • Raising the banks of the Moritzbach in Zwickau

    In October 2015, the official handover of the flood protection system on the Moritzbach in the Pölbitz district of Zwickau took place. Protective walls were strengthened and raised on around 530 metres of the watercourse.


    To the post
  • Linear shoring ensures large and safe working space

    Zur Sicherung der Baugrube und zur Erstellung des Sammlers verwendet das Unternehmen den gestuften Linearverbau von E+S.


    To the post
  • Dike Retrofitting in Michelau

    In total, a flood line of about 1,500 meters was created. The above-ground part was clad by the executing contractor with a lattice wall containing a filling of limestones.


    To the post