JUST-IN-TIME DELIVERY FOR A BRIDGE ABUTMENT

A new bridge for overpassing the A3 freeway was built at the Offenbach junction. There were a total of three excavation pits for this new construction.

A new bridge was built on the A3 autobahn near the Offenbach junction for the replacement of the autobahn overpass. For this new construction, a total of three excavation pits were required in axes 10, 20 and 30, which were constructed with sheet pile sections from thyssenkrupp Infrastructure.

The challenge here lay not so much in the supply, but rather in an ambitiously short time window from ordering the material to delivery. The customer's wish was to complete the excavation pits before the Christmas holidays.

Around 360 tons of sheet pile sections tkL 606 and 607 up to 15 meters in length, including seals and corner structures, were made available to the construction site for axes 10 and 30 in a period of less than two weeks from the order. Part of the material was in stock at the warehouse in Schaafheim, while another part of the sections had to be initially prepared at the plant in Ostrava in the Czech Republic, delivered and later processed at the warehouse.

The first delivery date was to be on December 9, 2020, but could be made as early as December 7. The last delivery was made on December 16. All in all, just-in-time deliveries took only a good week and a half and the excavation pits were completed as requested. In March 2021, the last 100 tons of tkL 605 for axis 20 were finally delivered on schedule.

Data & Facts

Material
460 t Spundwand TKL 605, 606 and 607 to 15 m Length 200 m Corner Constructions
Seal
4.500 m Bitumen Seal
Client
Heinz Schnorpfeil Bau GmbH, Treis-Karden
Executing Construction Company
Grundbau Jansen GmbH, Linnich

you might also be interested in

  • Protecting valuable history with terra stop log system

    In a major project here in the hinterland of the Elbe, a combination of a new earth embankment and strengthening of the protective measures by means of demountable stop log elements has been realised.


    To the post
  • Flood Protection for the Yuyao Community in China

    In the municipality of Yuyao, the Yuyao River was equipped with mobile flood protection along a length of about 4,700 metres to improve the quality of life of the citizens.


    To the post
  • E+S Linear Shoring: Sewer Rehabilitation Work in Leipzig

    The main components of the project included the construction of a storage channel with bottom relief made of semi-prefabricated parts in panel construction.


    To the post