Steel Section - Sheet Piling

JUST-IN-TIME DELIVERY FOR A BRIDGE ABUTMENT

A new bridge for overpassing the A3 freeway was built at the Offenbach junction. There were a total of three excavation pits for this new construction.

A new bridge was built on the A3 autobahn near the Offenbach junction for the replacement of the autobahn overpass. For this new construction, a total of three excavation pits were required in axes 10, 20 and 30, which were constructed with sheet pile sections from thyssenkrupp Infrastructure.

The challenge here lay not so much in the supply, but rather in an ambitiously short time window from ordering the material to delivery. The customer's wish was to complete the excavation pits before the Christmas holidays.

Around 360 tons of sheet pile sections tkL 606 and 607 up to 15 meters in length, including seals and corner structures, were made available to the construction site for axes 10 and 30 in a period of less than two weeks from the order. Part of the material was in stock at the warehouse in Schaafheim, while another part of the sections had to be initially prepared at the plant in Ostrava in the Czech Republic, delivered and later processed at the warehouse.

The first delivery date was to be on December 9, 2020, but could be made as early as December 7. The last delivery was made on December 16. All in all, just-in-time deliveries took only a good week and a half and the excavation pits were completed as requested. In March 2021, the last 100 tons of tkL 605 for axis 20 were finally delivered on schedule.

Data & Facts

Material
460 t Spundwand TKL 605, 606 and 607 to 15 m Length 200 m Corner Constructions
Seal
4.500 m Bitumen Seal
Client
Heinz Schnorpfeil Bau GmbH, Treis-Karden
Executing Construction Company
Grundbau Jansen GmbH, Linnich

you might also be interested in

  • Dresden-Gholis Flood Protection System

    In the years 2002 and 2013, the Gohlis district of Dresden was completely flooded by the river Elbe. To permanently protect this part of town, we installed a complete flood protection system.


    To the post
  • 90 seconds for 1 meter of security

    The new system is characterized by its fast installation without the need for special training. One meter of safety “grows” every 90 seconds.


    To the post
  • Feeder Line

    Old manholes were uncovered and demolished, and in the course of laying the new pipeline, the original structures were replaced by new manholes made of precast reinforced concrete.


    To the post